Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Tuesday, June 18, 2013

Trench Paving Postponed

Yesterday a post was created stating that trench paving was going to begin today (Tuesday, June 18th). We got late notice that this work is now postponed to Wednesday, June 19th.

There might be some work on-site in preparation for the trench paving, but the work has been postponed.